Bickering Spanish and Chinese firms put DRC dam project in peril
Inga III dam would be the biggest hydroelectric power station on the Congo river and provide electricity to DRC and other nations, including SA
28 October 2019 - 12:02
byMichael J Kavanagh and William Clowes
Support our award-winning journalism. The Premium package (digital only) is R30 for the first month and thereafter you pay R129 p/m now ad-free for all subscribers.
Kinshasa — Serious disagreements between groups of Spanish and Chinese developers that want to build an 11,000MW hydropower plant in Democratic Republic of Congo (DRC) may scuttle plans for the $14bn project, according to a report.
The Inga III dam would be the biggest hydroelectric power station on Africa’s second-longest river and provide much-needed electricity to DRC and other nations, including SA. After the Congolese government in 2017 asked two competing groups — one Chinese, one Spanish — to merge, the partners submitted a joint proposal in November 2018.
However, they were unable to agree on the project’s development and the percentage of each party’s share, the main company in the Chinese consortium, China Three Gorges, said in a September 20 letter to Bruno Kapandji, the head of DRC’s Agency for the Development and Promotion of the Grand Inga Project, or ADPI. The letter was published Monday in a report from New York University’s Congo Research Group and Belgium-based advocacy organisation Resource Matters.
Inga III is part of a long-delayed plan known as Grand Inga that’s eventually intended to harness as much as 40,000MW of power from the Congo River. Management of the project was criticised under former President Joseph Kabila for its lack of transparency. In July 2016, the World Bank halted a $73m grant for environmental and social studies after Kabila put the Inga agency under his direct control.
Two dams built on the same stretch of the Congo River more than three decades ago, Inga I and Inga II, still provide most of the nation’s power.
‘Reopen dossier’
The near-collapse of the current group of developers provides an opportunity for Kabila’s successor, Felix Tshisekedi, “to completely reopen the Inga III dossier, both in terms of its own capacity as well as that of its investors”, the Congo Research Group and Resource Matters said in the report.
“This ambitious project must be revisited to ensure that the Congolese population benefits from it,” they said.
Nobody answered the phone at the offices of China Three Gorges in DRC’s capital, Kinshasa. The company that heads the Spanish consortium, AEE Power, declined to comment. ADPI didn’t immediately respond to phone calls, text messages and e-mails.
Most of the electricity generated by Inga III is meant for SA, other African markets or DRC’s copper and cobalt miners. In 2013, SA committed to purchasing 2,500MW generated by the facility and late in 2018 indicated it might double that amount.
While Kabila appointed the Chinese and Spanish groups as co-developers a year ago, Tshisekedi, who assumed office in January, has yet to approve the consortium’s bid, and the partners are waiting to hear whether they will be granted exclusive rights to finance technical, environmental and social studies, as well as attract lenders.
The government, meanwhile, may consider scaling back Inga III to an earlier, 4,800MW design the Spanish and Chinese partners don’t see as economically viable. At a conference hosted by DRC’s presidency in August, Maximilien Munga, head of the energy ministry’s project co-ordination and management unit, said the smaller version was “underpinned by proven demand” and could be completed faster.
Visits halted
China Three Gorges said in the letter that it “remains ready to actively co-operate with the Congolese party to develop Inga III”. However, “important problems in China and the Ebola epidemic in your country” have prevented executives from visiting DRC, it said.
DRC has struggled to contain the second-worst Ebola outbreak, which has killed more than 2,100 people since it was first discovered in August 2018.
Support our award-winning journalism. The Premium package (digital only) is R30 for the first month and thereafter you pay R129 p/m now ad-free for all subscribers.
Bickering Spanish and Chinese firms put DRC dam project in peril
Inga III dam would be the biggest hydroelectric power station on the Congo river and provide electricity to DRC and other nations, including SA
Kinshasa — Serious disagreements between groups of Spanish and Chinese developers that want to build an 11,000MW hydropower plant in Democratic Republic of Congo (DRC) may scuttle plans for the $14bn project, according to a report.
The Inga III dam would be the biggest hydroelectric power station on Africa’s second-longest river and provide much-needed electricity to DRC and other nations, including SA. After the Congolese government in 2017 asked two competing groups — one Chinese, one Spanish — to merge, the partners submitted a joint proposal in November 2018.
However, they were unable to agree on the project’s development and the percentage of each party’s share, the main company in the Chinese consortium, China Three Gorges, said in a September 20 letter to Bruno Kapandji, the head of DRC’s Agency for the Development and Promotion of the Grand Inga Project, or ADPI. The letter was published Monday in a report from New York University’s Congo Research Group and Belgium-based advocacy organisation Resource Matters.
Inga III is part of a long-delayed plan known as Grand Inga that’s eventually intended to harness as much as 40,000MW of power from the Congo River. Management of the project was criticised under former President Joseph Kabila for its lack of transparency. In July 2016, the World Bank halted a $73m grant for environmental and social studies after Kabila put the Inga agency under his direct control.
Two dams built on the same stretch of the Congo River more than three decades ago, Inga I and Inga II, still provide most of the nation’s power.
‘Reopen dossier’
The near-collapse of the current group of developers provides an opportunity for Kabila’s successor, Felix Tshisekedi, “to completely reopen the Inga III dossier, both in terms of its own capacity as well as that of its investors”, the Congo Research Group and Resource Matters said in the report.
“This ambitious project must be revisited to ensure that the Congolese population benefits from it,” they said.
Nobody answered the phone at the offices of China Three Gorges in DRC’s capital, Kinshasa. The company that heads the Spanish consortium, AEE Power, declined to comment. ADPI didn’t immediately respond to phone calls, text messages and e-mails.
Most of the electricity generated by Inga III is meant for SA, other African markets or DRC’s copper and cobalt miners. In 2013, SA committed to purchasing 2,500MW generated by the facility and late in 2018 indicated it might double that amount.
While Kabila appointed the Chinese and Spanish groups as co-developers a year ago, Tshisekedi, who assumed office in January, has yet to approve the consortium’s bid, and the partners are waiting to hear whether they will be granted exclusive rights to finance technical, environmental and social studies, as well as attract lenders.
The government, meanwhile, may consider scaling back Inga III to an earlier, 4,800MW design the Spanish and Chinese partners don’t see as economically viable. At a conference hosted by DRC’s presidency in August, Maximilien Munga, head of the energy ministry’s project co-ordination and management unit, said the smaller version was “underpinned by proven demand” and could be completed faster.
Visits halted
China Three Gorges said in the letter that it “remains ready to actively co-operate with the Congolese party to develop Inga III”. However, “important problems in China and the Ebola epidemic in your country” have prevented executives from visiting DRC, it said.
DRC has struggled to contain the second-worst Ebola outbreak, which has killed more than 2,100 people since it was first discovered in August 2018.
Bloomberg
DRC hydropower scheme will be an ‘indefensible cost’ for South Africans
Inga dam dream could be a nightmare
SA weighs up doubling amount of power it will buy from Inga 3 in DRC
Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.
Please read our Comment Policy before commenting.
Most Read
Related Articles
Will DRC finally realise its plans for huge hydroelectric scheme?
AfDB under pressure to pull out of Grand Inga project
SA weighs up doubling amount of power it will buy from Inga 3 in DRC
LETTER: Inga wrong way forward
Inga 3 dam delays a chance for DRC to weigh options
Published by Arena Holdings and distributed with the Financial Mail on the last Thursday of every month except December and January.