Eskom, which supplies almost all of its electricity from coal-fired power plants, is considering spending R106bn ($7.2bn)) on wind and solar energy by 2030.

The investment plan, which Eskom could carry out by itself or in partnerships, is the most detailed demonstration yet of the utility’s ambition to move away from coal by taking advantage of SA’s abundant wind and solar resources.

The state-owned company envisages spending R61.75bn on wind power and R44.25bn on solar energy by the end of the decade, a company presentation seen by Bloomberg shows. Some of the projects are planned on the sites of coal-fired plants that are scheduled to close. Eskom confirmed the presentation and the costs without giving further detail.

The potential investment is part of a plan previously communicated by CEO Andé de Ruyter to borrow money from development-finance institutions for projects that would reduce emissions from a company that accounts for two-fifths of SA’s greenhouse gas output.

While President Cyril Ramaphosa has set up a commission to advise him on climate change, Eskom’s plans have been publicly opposed by mineral resources & energy minister Gwede Mantashe, who says such a transition could eliminate thousands of coal-dependent jobs.

The presentation outlines three phases for the investment once funding and regulatory approvals have been secured. In the first phase, which would span from 2022 to 2023, 246MW of photovoltaic solar power could be built at the Arnot, Duvha, Lethabo, Majuba and Tutuka coal-fired power plants.

A further 100MW of solar-generation capacity could be built at Komati, the first of the ageing power plants slated to close, and 19.5MW of solar power at the site of the Sere windpower plant.

The second phase, which would last from 2023 to 2025, could see the construction of a 750MW concentrated solar power plant at Olyvenhoutsdrift in the Northern Cape and 600MW of photovoltaic power added at Sere.

The company may also seek to build 300MW of wind power at Kleinzee on the northwest coast and 200MW of wind power at Aberdeen in the Eastern Cape .

A further 250MW of renewable energy generation capacity could be built on the sites of decommissioned coal-fired power plants.

The third phase envisages the building of a further 2,950MW  of solar photovoltaic capacity between 2025 and 2030, as well as 3,100MW of wind power.

Eskom already has debt of about R400bn, mainly from an overrun in the cost of construction of two coal-fired power plants. Debt from development-finance institutions is generally cheaper than borrowings from commercial lenders.

Bloomberg News. More stories like this are available on bloomberg.com

subscribe Support our award-winning journalism. The Premium package (digital only) is R30 for the first month and thereafter you pay R129 p/m now ad-free for all subscribers.
Subscribe now

Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.

Speech Bubbles

Please read our Comment Policy before commenting.