The Sebokeng Driver’s Licence Testing Centre (DLTC) was supposed to open in 2021. Work started in September 2015 and R78m was spent.

Answering questions in the Gauteng Provincial Legislature in 2021, then MEC for roads and transport Jacob Mamabolo said a company that was initially employed to construct the centre experienced cash flow issues in about 2018 and this resulted in a formal dispute.

“During the dispute resolution process, the contractor abandoned the site, which led to the site being vandalised. The contract was subsequently terminated in August 2019 for abandoning site and poor performance,” Mamabolo said.

“It is worth nothing now,” says Kingsol Chabalala DA member of the provincial legislature (MPL) for eMfuleni North. “The provincial government says it will need about an additional R91m to refurbish it, which means the money has gone down the drain.”

The centre was meant to help people in Sebokeng and surrounding areas who were struggling to get licences. Residents have to spend about R100 to travel to Vanderbijlpark to write their learner’s licence test.

Now, overgrown grass and weeds cover the area. Pipes and stacks of building blocks stand unused. There is rubble inside and the ceilings and the bathrooms have been vandalised.

According to Chabalala, there are security guards but vandalism is ongoing. A guard, who wished to stay anonymous, said they had been guarding the place since 2020, but no-one had ever come to check. He said three guards were on day shift and three on night shift.

“We were excited when construction of this licence centre started, because we thought finally as young people from this area we will have an essential service close to us,” said Lufuno Mutshinya.

He had to get his licence at Vanderbijlpark and “spent a lot of money going up and down”.

“It’s sad to see it crumbling to the ground now, though it was finished. Vandals have stripped everything inside the place and it doesn’t look safe,” he said.

The Gauteng department of infrastructure development referred GroundUp to the national department of roads and transport. Questions sent to that department to clarify the budget needed to fix the centre have gone unanswered.

GroundUp

subscribe Support our award-winning journalism. The Premium package (digital only) is R30 for the first month and thereafter you pay R129 p/m now ad-free for all subscribers.
Subscribe now

Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.

Speech Bubbles

Please read our Comment Policy before commenting.