Addis Ababa — Ethiopia began producing electricity on Sunday from its Grand Ethiopian Renaissance Dam (GERD), a multibillion-dollar hydropower plant on the River Nile that neighbours Sudan and Egypt have worried will cause water shortages downstream.
After flicking a digital switch to turn on the turbines in the first phase of the project, Prime Minister Abiy Ahmed sought to assure those nations that his country did not wish to harm their interests.
“Ethiopia’s main interest is to bring light to 60% of the population who is suffering in darkness, to save the labour of our mothers who are carrying wood on their backs in order to get energy,” Abiy said.
Abiy’s government says the project is key to its economic development, but Egypt and Sudan depend on the waters of the Nile and have worried it will affect them.
Egypt’s foreign ministry accused Ethiopia of further violation of a preliminary deal signed between the three nations in 2015, prohibiting any of the parties from taking unilateral actions in the use of the river's water.
The first violations of the initial agreement related to the filling of the dam, the ministry said in a statement on Sunday.
There was no immediate comment from Sudan.
Ethiopia, the second most populous country on the continent, has the second biggest electricity deficit in Africa according to the World Bank, with about two thirds of the population of about 110-million lacking a connection to the grid.
The project will ultimately cost $5bn when it is completed and become the biggest hydropower plant in Africa by generating 5,150MW of electricity, some of which will be exported to neighbouring nations, the government says.
The government has so far invested more than 100-billion Ethiopian birr ($1.98bn) in the project, state-affiliated FANA broadcaster reported. It is located at a place called Guba in the western Benishangul-Gumuz region.
Support our award-winning journalism. The Premium package (digital only) is R30 for the first month and thereafter you pay R129 p/m now ad-free for all subscribers.
Ethiopia’s Abiy Ahmed switches on the turbines at Nile mega dam
Prime minister inaugurates electricity production from the country’s often controversial multibillion-dollar Grand Ethiopian Renaissance Dam
Addis Ababa — Ethiopia began producing electricity on Sunday from its Grand Ethiopian Renaissance Dam (GERD), a multibillion-dollar hydropower plant on the River Nile that neighbours Sudan and Egypt have worried will cause water shortages downstream.
After flicking a digital switch to turn on the turbines in the first phase of the project, Prime Minister Abiy Ahmed sought to assure those nations that his country did not wish to harm their interests.
“Ethiopia’s main interest is to bring light to 60% of the population who is suffering in darkness, to save the labour of our mothers who are carrying wood on their backs in order to get energy,” Abiy said.
Abiy’s government says the project is key to its economic development, but Egypt and Sudan depend on the waters of the Nile and have worried it will affect them.
Egypt’s foreign ministry accused Ethiopia of further violation of a preliminary deal signed between the three nations in 2015, prohibiting any of the parties from taking unilateral actions in the use of the river's water.
The first violations of the initial agreement related to the filling of the dam, the ministry said in a statement on Sunday.
There was no immediate comment from Sudan.
Ethiopia, the second most populous country on the continent, has the second biggest electricity deficit in Africa according to the World Bank, with about two thirds of the population of about 110-million lacking a connection to the grid.
The project will ultimately cost $5bn when it is completed and become the biggest hydropower plant in Africa by generating 5,150MW of electricity, some of which will be exported to neighbouring nations, the government says.
The government has so far invested more than 100-billion Ethiopian birr ($1.98bn) in the project, state-affiliated FANA broadcaster reported. It is located at a place called Guba in the western Benishangul-Gumuz region.
Reuters
Sudan warns again about Nile Dam hydropower plan
Ethiopia completes second filling of controversial Nile dam
Egypt and Sudan sound alarm as Ethiopia resumes filling Nile dam
Would you like to comment on this article?
Sign up (it's quick and free) or sign in now.
Please read our Comment Policy before commenting.
Most Read
Related Articles
Filling of Ethiopia dam heightens tension with Egypt, Sudan
How developing border region in Sudan could ignite Africa’s next conflict
Published by Arena Holdings and distributed with the Financial Mail on the last Thursday of every month except December and January.